Modelling of Cost Overruns in Building Projects

MODELLING OF COST OVERRUNS IN BUILDING PROJECTS


ABSTRACT

Construction of building projects is an endeavour that involves capital expenditure, which is either borrowed or self-financed by clients. The expected outcome of such expenditure is value for money, which is usually dictated by project objectives of cost, time and quality. Project cost, as a project objective, is a crucial determinant of project success in the prevailing economic challenges being experienced globally. Construction cost overrun has become a reoccurring phenomenon in the delivery of building projects. The major thrust of this study was to identify, analyse and model the factors that contribute to building construction cost overruns in Abuja. The study adopted a Monte-Carlo technique in simulating cost overrun using DiscoverSim® version 1.1 (SigmaXL, 2013) simulation and RiskAmp Microsoft Excel add-in software to analyse data obtained from literature review, review of project documents with contract sum of over Five Million Naira executed within Abuja city in addition to interview sessions with construction professionals.

The study revealed that significant cost overruns are mainly due to re-measurement and variation. The simulation result elucidated that less than 10% of building projects are completed below the initial contract sum in Abuja which could be due to the fact that projects tend to be initiated and executed without adequate project information such as client brief, design details and specifications. The study recommends the need for minimizing occurrence of re-measurement in building projects through provision of full design information prior to contract award, development of simulation model for specific project categories and establishment of a project cost overrun band that will enable a scientific measurement of project's value for money benchmarked against initial cost estimate.


CHAPTER ONE

1.0 Introduction

Globally, the construction sector is inundated with cost overruns in the delivery of building projects. This experience has brought about loss of clients' confidence in consultants, added investment risks, lack of ability to deliver value to clients, and disinvestment in the construction industry (Mbachu and Nkado, 2004).It is of essence that the objectives of a building contract are met to the contentment of the parties involved. Cost, time and quality are significant, interrelated and interdependent targets for achieving the objectives/goals expected of building contracts (Ashworth, 1999, Gould, 2002). Thus, it is crucial to keep up a proper balance between the three so that project outputs are realised on time, within the financial plan and with the requisite quality (Akinsola and Potts, 1998). However, it is an admitted fact that in Nigeria, the majority of contracts suffer undue time extensions and /or additional cost to the client and /or inadequate quality of work (Oluwole, 2008b).

Project cost overruns can be either avoidable or unavoidable. Overruns due to design plan or project management problems are avoidable because they could have reasonably been foreseen and prevented (Shanmugam et al., 2006). However, there are some unavoidable costs such as those due to unanticipated events which cannot reasonably be prevented. Cost overruns may add value to projects when extra work is done with the intention of producing a better output. Overruns may also add value when they involve work that was omitted from design plans but clearly needed to be done. However, some overruns may not add value and represent wasted money if they do not result in a better product.

Cost overrun of a project refers to the actual ‘cost increase' to the client during construction of a building project (Janaka, 1992). It is merely the difference between the value originally envisaged for the project and the value reflected in the final certificate. Cost overruns occur from overspending the allowances, making changes and encountering unforeseen problems. Proper planning can greatly reduce cost overruns.


CHAPTER TWO

2.0 Literature Review

2.1 Introduction

The review of relevant literature is the main topic of this chapter. A literature review covers theoretical and methodological contributions to a certain issue in addition to the state of knowledge at the time of writing. It provides information about the state of the art in relation to the subject you are writing about. It examines the body of work on the chosen subject. The literature evaluation in this study comprises the …


Procedure for Downloading the PDF (Docx) Material


Modelling of Cost Overruns in Building Projects can be downloaded by requesting the full set of materials at the project or seminar cost. The document will be sent via Microsoft Word (MS-Word) format via WhatsApp (e-mail) following payment confirmation.


Seminar Material Cost
₦3,000
Project Material Cost
₦5,000


Request Complete Material

Complete Material Chapters of Modelling of Cost Overruns in Building ProjectsClick here to request the Complete Material via WhatsApp including;
  • Preliminary Pages,
  • Chapter 1-5,
  • References and Appendix.



Disclaimer for Complete Material Utilization

The displayed research work titled "Modelling of Cost Overruns in Building Projects" is stated as a research guideline towards accomplishing your assigned project / seminar research work. All the research materials on this website are ONLY for research purposes and should be used as a guideline in developing your research work. For no reason should you copy word for word as projectlist.com.ng will not be liable for any who copied the material. By ordering the complete research guideline, it signifies that you've accepted our terms of service.


Frequently Asked Questions (FAQ)


Can the material for “Discipline in the Public Service in Nigeria” be used as a guide for Public Administration (PA) Project?

Yes it can be used — The topic of this study was discipline in the public service of Enugu, state. (A Case study of ministry of Justice, Enugu). The study made use of both primary and secondary sources of data. The questionnaire was developed based on the four research questions. The population of the study was 307 (Three hundred and Seven) staff of both ministry of Justice and civil service commission, Enugu. The sample size was 174 (one hundred and seventy − four). The sample technique used was stratified random sampling. The instrument used for gathering data for the study was questionnaire which was structured. The instrument was tagged discipline in the public service descriptive questionnaire (DPSD). The validity of the instrument was tested using pilot …


Can the material for “Design and Implementation of a Web Based System for Sales and Inventory Management” be used as a guide for Computer Science (CS) Project?

Yes it can be used — A sales and inventory system is a software-based business solution used to simultaneously track sales activity and inventory. Computerized sales and inventory systems save time for businesses by speeding up transactions while raising accuracy. The aim of the study is to design and implement a web based application that will manage the sales and inventory on goods and services. In achieving this aim, the following specific objectives were laid out to create a database that will help store sales records and develop an independent user application software. The motivation that led to the implementation of the proposed system is that the recording of sales and cash received are done manually on the book that appear rough, inaccuracies in record keeping …


Is the topic “Design and Implementation of an Online Birth Rate Monitoring Information Record System” recommended for Computer Science (CS) Project?

Yes it is highly recommended — Birth registration and monitoring is part of national civil registration systems that also record marriages and deaths. The aim of the study is to design and implement an Online Birth Rate Monitoring Information Record System. In achieving this aim, the following specific objectives were laid out to develop an online system that can be easily used to register births and implement a system that can be used to obtain reports of birth rate. The motivation that led to the implementation of the proposed system is as a result of the difficulty encountered in determining the birth rate in different regions and time consumption during manual recording of birth rate information. The methodology adopted in this study is the structured system …


Is the topic “The Need for Planning in an Organization” recommended for Public Administration (PA) Project?

Yes it is highly recommended — This project work is found out of principal factors responsible for the ineffectiveness of planning system in government organization. The objective of the study is to analyze the entire planning system of the organization under study, highlight areas of ineffectiveness in the organization for corrective measures and procedures. To determine whether the system provide effective reporting requirements to management for use in planning, controlling and future operation. To ascertain whether the planning system of mining organization comply with planning standards are under laid down regulations or not. The research work sill enable all department within the organization to acquaint themselves with the organization and other third parties to have knowledge on the system of keeping and maintain record of planning …


Can the material for “The Impact of Exchange Rate Fluctuation in International Trade in Nigeria” be used as a guide for Business Administration and Management (BAM) Project?

Yes it can be used — The impact of exchange rate fluctuations on international trade in Nigeria is a topic chosen from exchange rate on international trade field. The research was conducted mainly to examine the exchange rate fluctuation on international trade in Nigeria for effective research on this topic; both primary and secondary data were sued to elicit Information from sample studied, the primary source of data were responses from personal in ferried while secondary source were from periodic journals and newspapers. Two hundred persons were interviewed as the sample of exporters with exchange rate fluctuation and data analysis were based on oral interview and the major findings are as follows; that exchange rate fluctuation has a negative effect on agricultural exports thus the more the exchange …


Can the material for “Niger Delta Crises and National Security in Nigeria: Appraisal of the Amnesty Programme” be used as a guide for Political Science Project?

Yes it can be used — The Niger Delta − the geographical heart of oil production in Nigeria has been a breeding ground for militants for some years now. This is because the discovery of oil and its exploitation has ushered in a miserable, undisciplined, decrepit, and corrupt form of ‘petro-capitalism’ which produces conflict accelerating factors. Devastated by the ecological costs of oil spillage and underdevelopment, the Niger Delta has become a centre of violence. In an attempt to solve the Niger Delta crisis, the Federal Government recently introduced the policy of amnesty to militants as the solution to the Niger Delta Crisis. The study assessed the Amnesty Programme which is basically a Disarmament, Demobilization and Reintegration (DDR) to the Niger Delta militants and effect on …


Can this topic “Design and Implementation of Online Admission and Result Checking System” be used for Computer Science (CS) Project?

Yes it can be utilized for research — In every institution, admission and result are the most important data which is the basic for each candidate. The institution makes sure that every student comes into the institution through a verified process. On the other hand, the institution makes sure that every qualified student who is duelyadmitted, goes out with a comprehensive result so as to ascertain his/her studentship. The major aim of this project is to enable the institution produce qualify students that is students who did not come into the institution through falsification of result and who did not graduate with a maneuvered result. All these will be achieved by using a system which its operation is not basically manual. …


Can this topic “The Moral Decadence in Nietzsche’s Philosophical Writings” be used for Philosophy Project?

Yes it can be utilized for research — The study scrutinizes the Moral Decadence in Nietzsche's Philosophical Writing. Thus the major task of this work is to assess the religious and moral demise of Nietzsche and restore the supreme value to its place in the world. Nietzsche's writing spans philosophical polemics, poetry, cultural criticism, and fiction while displaying a fondness for aphorism and irony. Nietzsche identifies is his constant critique of morality all throughout his work. Down the stages of the history of philosophy, the modern philosophy of consciousness, attention has been directed to the mastery of the natural world. This is a period whose character of rational optimism was diametrically opposed to tradition and authority upon which stood the veracity and logic of primitive religion. It has …


Can the material for “A Pragmatic Interpretation of Child Language” be used as a guide for English Language Project?

Yes it can be used — This thesis titled “A Pragmatic Interpretation of Child Language: A Case Study of Telegraphic Speech has been carried out to determine the role of context in understanding language use by children or children‟s speech. Pragmatics is the study of speaker context meaning…. It is a component of linguistic study that goes beyond grammatical competence or well formed sentence to find meaning for a particular utterance or discourse exchange. It demonstrates the relationship between what speakers say and what they actually mean and the kind of effects they expect on the minds of the hearers. The motivation for the study emanates from the fact that children‟s utterances are not easily understood, especially when one is not familiar with the child‟s background …


Can the material for “Production Cost Control in Manufacturing Organisation” be used as a guide for Banking and Finance (BF) Project?

Yes it can be used — This research work is based on the production cost control in manufacturing organization. The study was motivated on how to control cost in manufacturing industries in order to achieve the purpose of which the industry is establish. To solve the research problem the researchers made use of only secondary source of data, since the guidelines for writing the ND research work in banking and finance was restricted to secondary source of data. The research instrument used to collecting the data were textbook, journal, magazine, newspaper. Etc. Also, based on data collection form secondary soruce, it is quite obvious that I have found out that for production cost control to fully and well carried out, there should be combination of man and material resources in …



Chat with us on WhatsApp