The Impact of Delayed and Disrupted Construction Projects on the Cost of Building Construction in Nigeria

THE IMPACT OF DELAYED AND DISRUPTED CONSTRUCTION PROJECTS ON THE COST OF BUILDING CONSTRUCTION IN NIGERIA


ABSTRACT

Construction projects refer to the projects undertaken by the construction industry to provide the much needed infrastructures for national development. The study was carried out to investigate The Impact of Delayed and Disrupted Construction Projects on the Cost of Building Construction in Nigeria using Enugu State as a case study. In achieving this aim, the following specific objectives were laid out to determine the effects of delay and disruption on the cost of building construction project in Nigeria, ascertaining the cost, which aim at x-raying unnecessary delay and disruption in the normal processes of procuring and prosecuting building and civil engineering construction work at both pre-contract and post contract stages of construction. Delays and disruptions are among the challenges faced in the course of executing construction projects. Delays as well as disruptions are sources of potential risks that current studies are looking into ways to manage. Delays and disruptions have had effects to construction projects. The factors that usually call for these delay and disruption in construction projects of the numerous project on the construction landscape and on the parties that are involved in carrying out the projects. This study continued with elucidating what the Quantity Surveyor and the other parties involved in the construction process can do to eliminate delays and disruption in construction in Nigeria. This study will be beneficial to the most construction industry in Nigeria because once a project is initiated and manage properly it will eliminate high cost of procurement and a lot profit are involved. Based on the findings, it is recommended that adequate construction budget, timely issuing of information, finalization of design and project management skills should be the main focus of the parties in project procurement process.


CHAPTER ONE

1.1 Introduction

Delay as referred in construction is prolonged construction period and disruptions are events that disturb the construction programme. Delays and disruptions are among the challenges faced in the course of executing construction projects. Delays as well as disruptions are sources of potential risks that current studies are looking into ways to manage. Delays and disruptions have had effects to construction projects. The Construction industry can be described as a collection of loosely integrated firms involved in the provision of the materials for the construction of structures, designing facilities to be constructed, constructing the facilities, installation of specialized services in the constructed structures, and supervision of the constructions in the areas of building and civil engineering works.

As a prelude to other parts of this study, this chapter will discuss the background upon which this study was initiated, the statement of problems that led to this study, the Aim and Objectives of the study. Others are Significance of the study, Scope of work, Research hypothesis and questions, Limitations of the Study and Definition of technical terms.


1.2 Background of Study

Construction projects refer to the projects undertaken by the construction industry to provide the much needed infrastructures for national development. Cost overrun is a term used to express situations when actual cost of a project exceeds the budgeted cost. Time overrun is a situation when the actual completion date outpaced the scheduled completion date. The budgeted cost and scheduled completion date most often are not positively achieved by the contractor. More time and money are usually required to complete the construction of a project. Cost-and time-overruns in construction projects negatively impacts on the important role the construction industry plays in any given economy, especially developing economies such as Nigeria’s.

Delays and disruptive in construction has some effects on its cost and very retrogressive in a developing economy like Nigeria and needs to be properly addressed and tackled with all the courage and effort that we can muster.

Most town and cities in Nigeria are dotted with projects that are being delayed, disrupted, and uncompleted. Explanations giving for the stages of each buildings project is varied and sometimes attributed to lack of financial, human and material resources with which to execute the projects. It is common in Nigeria especially now that the country is suffering from depression in the economy. It is often bad to see huge capital investments being disrupted and abandoned. Any attempt to delay and disrupt a construction project; will have terrible consequences on every aspect of the nation's activities which will be severe and unwelcome.

Therefore, in Enugu State where the research was carried out, the activities that was conducted is to know the Impact of Delayed and Disrupted Construction Projects on the Cost of Building Construction in Nigeria.


1.3 Statement of Problems

Investigation revealed that one of the biggest problems associated with most of the construction projects in Nigeria today is problem of delays and disruptions at both the pre-contract and post-contract stages of construction in building and civil engineering works. The cost of building increases at the cause of delays and disruption in construction because of variation. Many construction project in Enugu needed huge capital outlay and time to execute them and any attempt to delaying and disrupting the construction proper will result to terrible consequences that will affect the economical control and building cost.

The demand for more construction of all types, coupled with a tight monetary supply has provided the construction industry with a big challenge to cut costs. The problem of high contract costs of all aspects of construction is becoming obvious. Consequently, substantial increases are being observed in projects. This substantial increase has brought about loss of client confidence in consultants, added investment risks, inability to deliver value to clients, and disinvestment in the construction industry.


1.4 Aim and Objectives of Study

The aim of the study is to investigate the Impact of Delayed and Disrupted Construction Projects on the Cost of Building Construction in Nigeria using Enugu State as a case study. In achieving this aim, the following specific objectives were laid out as follows:

  1. To ascertain the effects of delays and disruptions on cost of building construction.
  2. To investigate into most delayed and disrupted construction projects.
  3. To examine the effect of fluctuation in prices on construction projects costs.
  4. To examine the effects of variation in design on construction project costs.
  5. To examine the costs of delayed and disrupted construction project to clients, contractors, the professionals that are engaged and the nation, in particular Enugu state.

1.5 Research Questions

The study came up with research questions so as to be able to ascertain the above stated objectives. The specific research questions for the study are stated below as follows:

  • Do fluctuations in prices bring about changes in construction project cost?
  • In what ways can variations in design affect construction cost?
  • What are the causes of delays and disruptions in construction projects?
  • What are the effects of delays and disruptions on building construction project cost?
  • What the costs are of delayed and disrupted construction projects to the clients, contractors, the professionals that are engaged in the field?

1.6 Research Hypothesis

In order to pursue the objective of this study, the following generalized statements have been designed to guide and aids in obtaining the result for the experiment to be conducted. For this work, the null hypothesis will be represented with H0 while the alternative hypothesis will be represented with hypothesis H1.

Hypothesis One

  • H0: Delays and disruptions have no significant effect on building construction projects.
  • H0: Delays and disruptions have significant effect on building construction projects.

Hypothesis Two

  • H0: There is no significant factor instigating the delays and disruptions on cost of building construction in Nigeria.
  • H1: There is a significant factor instigating the delays and disruptions on cost of building construction in Nigeria.

1.7 Significance of Study

This study will be beneficial to the most construction industry in Nigeria because once a project is initiated and manage properly it will eliminate high cost of procurement and a lot profit are involved.

Also this will help in planning and execution of future construction project executions, especially the quantity surveyor in the feasibility and planning stages of a proposed scheme and preparation of work method and schedules by the building manager.

The study also intend to bring together, the causes of construction delays and disruptions and also tries to ascertain the costs, which will help the construction firms, Engineers, Surveyors and construction managers to initialize and control their project without lost or poor management.


1.8 Scope of Study

The scope of the research is focused on the Impact of Delayed and Disrupted Construction Projects on the Cost of Building Construction in Nigeria using Enugu State as a case study.


1.9 Limitations of the Study

During the course of this study, many things militated against its completion, some of which are:

  1. Time Constraint: The time frame given to accomplish this project was very short due to school academic calendar and it was carried out under pressure which made the researcher not to implement some necessary features.
  2. Research material: availability of research material is a major setback to the scope of the study.
  3. Frequent power failure: This made the researcher append more money on fuel to ensure sustainable power.
  4. Financial Constraint: Insufficient fund tends to impede the efficiency of the researcher in sourcing for the relevant materials, literature or information and in the process of data collection (internet, questionnaire and interview).

1.10 Definition of Terms

Delay: Delay in construction can be defined as an act whereby projects execution is slow or interrupted one time or the other, thereby leading to unnecessary extension in the programme of work from what was initially scheduled.

Disruption: Disruption in construction projects can be defined as an act or sites partially or completely deserted at one time or the other for the reasons of certain exigencies which have resulted in prolonged delays which are not in accordance with the programme of work in use extension of time or postponement as initially scheduled.

Cost: The estimated amount of money that will be needed for something or the price that should be charged for something. Also, it implies the effort, loss or damage that is involved in order to do or achieve something.

Construction: The process or method of building or making something, especially road, building, bridges etc.


CHAPTER TWO

2.0 Literature Review

2.1 Introduction

The review of relevant literature is the main topic of this chapter. A literature review covers theoretical and methodological contributions to a certain issue in addition to the state of knowledge at the time of writing. It provides information about the state of the art in relation to the subject you are writing about. It examines the body of work on the chosen subject. The literature evaluation in this study comprises the …


Procedure for Downloading the PDF (Docx) Material


The Impact of Delayed and Disrupted Construction Projects on the Cost of Building Construction in Nigeria can be downloaded by requesting the full set of materials at the project or seminar cost. The document will be sent via Microsoft Word (MS-Word) format via WhatsApp (e-mail) following payment confirmation.


Seminar Material Cost
₦3,000
Project Material Cost
₦5,000




TABLE OF CONTENTS

PRELIMINARY PAGES


CHAPTER ONE

INTRODUCTION

  • 1.1 Introduction
  • 1.2 Background of Study
  • 1.3 Statement of Problems
  • 1.4 Aim and Objectives of Study
  • 1.5 Research Questions
  • 1.6 Research Hypothesis
  • 1.7 Significance of Study
  • 1.8 Scope of Study
  • 1.9 Limitations of the Study
  • 1.10 Definition of Terms

CHAPTER TWO

LITERATURE REVIEW

  • 2.1 Introduction
  • 2.2 Conceptual Review of Delay and Disruption
  • 2.3 Construction Delay and Causes
  • 2.3.1 Reason why Construction Projects are Delayed and Abandoned
  • 2.3.2 Common Problems Causing Delay in Construction
  • 2.3.3 Cause of High Costs of Construction
  • 2.3.4 Time Over-Runs and Cost
  • 2.4 Effects of Delays and Disruptions
  • 2.5 Theoretical Framework of Building Construction Delays and Disruptions
  • 2.6 Empirical Review of Related Literature
  • 2.7 Delay and Disruption in Construction in Summary

CHAPTER THREE

RESEARCH METHODOLOGY

  • 3.1 Introduction
  • 3.2 Research Design
  • 3.3 Area of Study
  • 3.4 Population of Study
  • 3.5 Sampling and Sampling Technique
  • 3.6 Validation of Research Instrument
  • 3.7 Method of Data Collection
  • 3.8 Method of Data Analysis
  • 3.9 Ethical Consideration
  • 3.10 Statistical Analysis

CHAPTER FOUR

DATA ANALYSIS, RESULT AND DISCUSSION

  • 4.1 Introduction
  • 4.2 Presentation and Analysis of Data
  • 4.3 Test of Hypothesis 1
  • 4.4 Test of Hypothesis 2
  • 4.5 Analysis of the Effects of Delays in Construction Projects
  • 4.6 Implication of the Findings
  • 4.7 Discussion of Findings

CHAPTER FIVE

SUMMARY, CONCLUSION AND RECOMMENDATION

  • 5.1 Introduction
  • 5.2 Summary of Findings
  • 5.3 Conclusion
  • 5.4 Recommendation
  • 5.5 Suggestion for Further Study

REFERENCES

APPENDIX A - “QUESTIONNAIRE”


Disclaimer for Complete Material Utilization

The displayed research work titled "The Impact of Delayed and Disrupted Construction Projects on the Cost of Building Construction in Nigeria" is stated as a research guideline towards accomplishing your assigned project / seminar research work. All the research materials on this website are ONLY for research purposes and should be used as a guideline in developing your research work. For no reason should you copy word for word as projectlist.com.ng will not be liable for any who copied the material. By ordering the complete research guideline, it signifies that you've accepted our terms of service.


Frequently Asked Questions (FAQ)


Can this topic “The Study of Motivation and Employee Productivity in Public Sector” be used for Public Administration (PA) Project?

Yes it can be utilized for research — The research work is concerned with the study of Motivation Employee Productivity in Public Sector, using the Ministry of Education as a case study. The main objective examines the effect of motivation on employees’ productivity in the Ministry of Education. Data were collected through structured questionnaire. Survey method was used to analyze the effect of motivation on employees’ productivity in the Ministry of Education and random sampling technique was used to stratify the sample population. Also, hypotheses were tested using simple mean statistics. It was found out that adequate staff motivation will enhance employees performance, that the higher the motivation the lesser the friction between boss and subordinate, that appreciation is a form of motivation for staff in the Ministry. That frequent …


Is the topic “Nigeria Stock Market as an Instrument in Mobilization of Investment Capital” recommended for Accountancy / Accounting Project?

Yes it is highly recommended — The study determines the Nigeria Stock Market as an Instrument in Mobilization of Investment Capital. In achieving this aim, the following specific objectives were laid out to contribution of the capital market to the development of industrial capabilities and economic growth, the possible strategies to enhance or increase capital market, the mission or objective of the Nigeria stock exchange in promoting increased capital information in Nigeria by the 2010, and the relevance or usefulness of stock market in the mobilization of investment capital. The research design used in this report is descriptive design, utilizing questionnaire method to obtain information from the respondents for this project. Primary data were collected from the primary source which questionnaire was used as an instrument …


Can this topic “Computerization of an Online Point of Sales (POS) System” be used for Computer Science (CS) Project?

Yes it can be utilized for research — Point of sale (POS) refers to the place where a customer executes the payment for goods or services and where sales taxes may become payable. The aim of the study is to design and implement a web based Point of Sale System for FPNO bookshop. In achieving this aim, the following specific objectives were laid out as follows that will develop an application software that will provide full functional reports to management and control the existing system errors made by human beings due to shortcomings. The motivation that led to the implementation of the proposed system is that the job of preparing sales record is tedious causes delay and the method encourages fraud figures are easily manipulated and changed. The …


Can the material for “Detection and Prevention of Financial Fraud in Nigeria Banks” be used as a guide for Banking and Finance (BF) Project?

Yes it can be used — Banks deal essentially in cash financial instruments and other documents which are generally of a negotiable and easily transferable in nature. Hence it is very pertinent to say that the exposure of the banks to both internal and external fraud is very great. This practices is very common to areas involving cash, cheques and fund transfer operations. Much research and thought are increasingly being directed towards the study of the causes of fraud in banks because of its effect on banking and the entire economy. Recent study carried out by financial Institute training centre, Lagos showed that cause of fraud reported annually between 1989 and 1998 was about 500 and the annual average money involved in attempted fraud was thirty − six …


Can the material for “Production of homemade carrot oil and its benefits” be used as a guide for Science Laboratory Technology (SLT) Project?

Yes it can be used — The purpose the research work is to examine the Production of Homemade Carrot Oil and Its Benefits. In achieving this sole aim, the following objectives were set out to; determine the benefits of homemade carrot oil, and provide adequate information about carrot oil usage, to avoid nausea, vomiting, abdominal cramps, diarrhea, and convulsions as a result of breast feeding babies. Carrot oil should never be used during pregnancy as it may cause uterine contractions and, in rare cases, miscarriage. The use of carrot seed for contraception and abortion has long been recorded in the historical medical literature, although the practice is considered unsafe and strongly advised against today. Its effect on breastfeeding babies is unknown and should be avoided. If …


Can the material for “Design and Implementation of a Computerized Library Stock Control System” be used as a guide for Computer Science (CS) Project?

Yes it can be used — A library management system software package is designed especially to handle book-keeping tasks and students entry and exits period. The aim of this study is to design software that will Design and implement a Computerized Library Stock Control System. In achieving this aim, the following specific objectives were laid out to Control the inflow and outflow of stock/materials in the library, store books using IDs assigned to each book, assist in the management and record library stocks and give account of borrowed and un borrowed books. The motivation that led to the implementation of the proposed system is as a result of poor determination books due and overdue, lack of comprehensive database for book stocked in the library and verifiable …


Is the topic “Influence of Visual Aids on Effective Teaching and Learning of Social Studies” recommended for Social Studies Education Project?

Yes it is highly recommended — This research work is designed to investigate “The influence of visual aids on effective teaching and learning of social studies”. It is carried out to proffer solutions to the problems emanated from the research work. The research was carried out in five different schools with the target population of 100 students and 20 teachers. 20 students are to be investigated (Appendix I) while questionnaire of ten items (Appendix II) were used to investigate the teachers. The findings revealed that, the influence of visual aids on effective teaching and learning of social studies can not be over-emphasized respondents. it is clear that availability of different types of visual aids in schools and its effective use to the maximum will surely go a …


Can the material for “The Impact of Public Sector Accounting on Government Revenue Generation and Expenditure Control on Public Funds” be used as a guide for Finance Project?

Yes it can be used — Government generate revenue in order to enable it perform its functions. This project is all about how government source for fund and how it spends it. It also focused on the need for expenditure control on public funds. In course of this project. this is to enable text books and journals wer used as materials for this project. this is to enable the researcher known the view of other authors on this study. Chapter one and two were based on the objectives and the problems of the study. Data used in this are through primary and secondary sources. The primary source include; oral interview and questionnaires Chapter three and four discussed the presentation and analysis of data testing of hypothesis and interpretation …


Can the material for “Problems of Facilities Management in Corporate Organizations” be used as a guide for Estate Management (EM) Project?

Yes it can be used — Facilities management in Nigeria is still in an early learning cycle when compared with the situation in Europe, USA etc where the practice has been on since the 1980’s. Some corporate organizations are increasingly embracing the need for efficient facilities management. Like any new venture, facilities management practice in Nigeria is expected to also have its commencement problems. This study examines the role of the facilities manager and highlights the problems that constrain effective facilities management. The research adopted both survey and case study methods. The survey was used in data collection while the case study was based on an intensive study of six selected drug, beverages and textile manufacturing industries in Lagos. The sampling technique used was simple random sampling. …


Is the topic “Water Level Monitoring and Control System using Ultrasonic Sensor” recommended for Mechatronics Engineering Project?

Yes it is highly recommended — The Water Level Controller System is an Electronic Equipment which when electrically connected to the starter of any given pump motor will control the operation of the pump depending upon the water level in the Source and Destination Storage Tanks. It can automatically switch ON and OFF the domestic water pump set depending on the tank water level. The aim of the study is to design and construct a Water Level Monitoring and Control System using Ultrasonic Sensor. In achieving this aim, the following specific objectives were laid out to construct a device that will control the flow and pumping of water in the overhead tank, and design a system that will control, monitor and maintain the water level in …



Chat with us on WhatsApp